on 07-31-2014 9:05 PM
A (0%) B (0%) and C(100%) are three aternative components, however one of them with zero % is considering for total cost in BOM, Does anyone have Idea why ? I expect just to consider in total cost the component C with 100% use
Hi Marco,
Try to check the Costing Relevancy of each component in the BOM item details tab "Status/Lng Text". For component with zero %, it should not be ticked.
Regards,
Julian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Marco
Thanks for sharing the correct answer!
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.