on 08-06-2014 9:40 AM
Hi
I am using DP90 transaction for resource related billing w.r.t sales order and project WBS. All spare parts are delivered w.r.t WBS network. And Time confirmation against WBS network . With DP90 I am creating Debit memo request. In Debit memo request all spares consumed are always flagged with 1 Qty. on the other hand labor hours are transferred correctly w.r.t quantity.
Please guide to resolve the issue.
Sanjeev
What error you getting. Please post screenshots of error.
OR Else you are looking for configuration of RRB?? then search in service.sap.com
Thank$
Hidayath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.