Hi,
We are having a requriement to check the budget at PO Deblocking ( Releasing ) Level, not at the time PO creation Level.
can anybody suggest is there any function module or standard settings available to check this.
Example :
PO Creation with F1+FC1+CI1
PO Should only show the budget if check button is pressed in the PO with deriving above account assignments based on the derivation tool.
and should not stop for saving the PO if budget is not available.
When deblcking the PO
system should check the budget and give the error message.
Thanks in Advance
SAM
08-07-2014 12:47 PM
Can be achieved with BADIs ME_COMMTMNT_PO_RELEV, ME_COMMTMNT_PO_REL_C. However, it is not applicable for service POs.