Dear SAP Gurus,
We are supporting consolidation activities for one of our clients in BPC 10.0. We started consolidation activities from Dec 2013 and henceforth for all the months till June 2014. All the controls Monitor and consolidation Monitor were with the status Passed and Done.
But now while trying to run July 2014 consolidation, we observe that the Controls Monitor has gone back to "to be executed " status while the consolidation has still the "Done" status.
2 activities were done after June 2014 consolidation i.e, we have increased the treshold limit for the controls available in the control set.
Also we have loaded data yesterday into system for July 2014, since there was problem with the data load coming from ECC cube to BPC cube for period July 2014, we have deleted that uploaded data (entire request of yesterday) in the BPC cube.
May I know what has caused the control status to goback to "to be executed" stage from "passed".
Could you kindly help me in resolving this issue.
Regards,
Shilpa
Hi Shilpa
As you noted when ever there is new data loaded into EPM, you need to execute the Control sets. If required you also need to run the consolidation process for current month for which data has been loaded.
Thanks
Ravi