Hi Experts,

where we can see the Asset link with particular Work-center.

we want to see under work center which asset is assign.

Thanks in advance

Kind regards

Pranav Kr. Gupta

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Pranav,

In asset master,Allocations tab, you will find a field equipment number.

Take the equipment number and pass it in T code IE03, there in location tab you will find workcenter.

This is the indirect link between asset and workcenter.

Hope it solves.

Regards,

GSR

amit_anasane
Active Participant
0 Kudos

Hi Pranav,

there is link between cost center and asset, also cost centers are linked to work centers, may be below report could be helpful to you S_ALR_87011966  by cost center, also one report which is linked to location S_ALR_87011968- by location.

Regards,

Amit Anasane