Hi guys
When I run CJ88 to settle WBS to AuC, the following error displayed:
Define a settlement cost element for receiver type FXA
Message no. KD506
Diagnosis
In allocation structure 88 (controlling area 9998), you did not define
which cost element should be used when settling costs/revenues of the
sender. Nor did you define receiver type FXA.
Procedure
Assign a different allocation structure to the settlement sender (->
Master data -> Settlement rule -> Goto -> Settlement parameters), or
maintain allocation structure 88.
How should I specificly maitain allocation structure 88 to assign a cost element ?
Thank you
Kiki
Hi Kiki,
Go to OKO6 and select allocation structure 88 and select assignments and define receiver category & select check box cost element in the settlement cost elements node for the assignment.
Regards,
Mukthar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Mukthar , Tejas
Thank you for your answers.
Yes, finally I found how to define settlement cost elements for allocation structure 88.
Regards
Kiki
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Are you using and of P & L account ? If yes please check as cost element might have been created with cost element category as 1 (Primary costs/cost-reducing revenues).
Hope this solves your issue else revert.
Regards,
Tejas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.