Backward scheduling - Goods Issue date is off by a day in STO

Former Member
0 Kudos

Transit Calendar Assignment has 6 workdays (Mon-Sat)

Requested Delivery Date is 9/25 and GR end date listed is 9/25 (Thursday)

Transit Time in Route is set to 6 days

However, when intercompany PO is being created, GI date it calculates is 9/17 (Wednesday) 10:00PM (end of the day's workshift) when based on the transit time of 6 days and considering Sunday is a non-working day, it should be 9/18 (Wednesday)


That is: Delivery date (9/25) - 6 work days (mon-sat) = 9/18, but it is calculating 9/17 very end of shift 10:00 PM

Any Idea why this may be? There no GR processing time set.

Thanks,

Akshat