Hello Gurus,
we have a group of workcenters(reactors) maintained in ECC.
No. of individual capacities :5
Utilization :100%
operating time :8hrs/day
Total bucket capacity per day = 40hrs
Now i have an operation in the recipe with this resource being assigned and the Total capacity required is 80hrs.
SNP PDS shows 2days for this activity based on the bucket capacity available which is 80/40 =2 days.
since we can use 1 capacity at a time for a specific order; System should be calculating 80hrs/8 hrs/day= 10Days.. No distribution keys maintained in ECC system.
how to fix the SNP PDS in APO- do we need to go with the enhancement option.
Please advice
thanks
Shyam
Hi Shyam,
If you enhance this, e,g. change the PDS, or change the order creation, then it also affects capacity leveling calculation results. If you can only use 1 capacity at a time for a specific order, why not to use single-mixed resource? For multimixed resource, the resource capacity will be always considered.
BR
Claire
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.