on 08-27-2014 3:01 PM
Dear Experts,
When I am creating Notification & selecting Priority, System gives pop-up “do you want to specify new dates?” If I select yes system automatically change required start & required end based on Priority.
Now my question is do we have same functionality for Maintenance order as priority field is available there (If we are directly creating a MO)?
Even if we are creating WO from notification, required start & end dates copies to Basic start & Basic finish but if we change priority then no change in basic start & finish dates. Why?
Greetings Parag,
You may select the Priority in the initial screen of IW31 and the dates will shift accordingly, if you maintained the Relative Start &/or Relative End in
SPRO > Plant Maintenance > Maintenance Processing > Maintenance & Service Orders > General Data > Define Priorities > Define Priorities for Each Priority Type
If you want to change date based on Priority on the Order header screen, it's not possible in the standard to my knowledge, but you may easily develop an enhancement utilizing the user exit
IWO10012 Maintenance order: Priority handling on central header
or
IWO10009 PM Order: Customer Check for 'Save' Event
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.