on 08-27-2014 5:59 PM
Hi All,
I am not getting a check box [on data change] with I am scheduling the workbook for query [query is build on multiprovider which contains target cube ZC_NCRPFP] cube is in BIA.
I have added the Trigger even data change in the process chain.
there I have checked the DTP (to determine the infoprovider].
Chain executed successfully.
Broadcaster log says.
1 InfoCubes determined by process type
Data change in InfoProviders: 0 registered settings found.
I am working with Bex 3.5, BW 730 Patch 9
HI Alnoor
For the DTP you should explicitly specify the InfoProvider. Otherwise, it is possible that the broadcaster does not recognize the InfoProvider and does not offer execution when data is changed for this InfoProvider in the Scheduling dialog box.
Thanks
Abhishek Shanbhogue
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I tried with 2 options on the same(Multiprovider with one infocube) query built on Multiprovider.
1) Added the trigger event with MPRO as infoprovider, activated and scheduled the process chain. in the schedule tab of broadcaster, i can see data change option to select the Mutliprovider.
2) instead of MPRO, added the infocube in the trigger event process type ,activated and scheduled the PC. this time ,i dont see the data change option in broadcaster.
So you please try with MPRO as infoprovirder once,since your query on the same.
Regards,
Sakthi
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.