Hello
In customizing for MRP (OPPQ), parameters for BOM explosion / routing selection is 3 (BOM explosion number/order start date).
In MRP4 view of material master, selection method for BOM explosion is 2 (Selection by production version).
No MRP group is assigned.
I have 3 production versions : one for 2014, one for 2015, one for 2016 :
I use a BOM explosion number with fixed key date 1st December 2015 :
When manually creating a planned order with dates in 2014 and explosion number EXP_1215 (fixed key date 1st December 2015), Production Version PV1 is selected (valid for 2014), but no routing is selected because explosion date is BOM explosion number, and in PV1 there is no valid routing in 2015 :
Is it possible to select production version according to explosion date, and not order dates ?
Hi Tristan,
are you aready try setting :
3 | Selection only by production version in MRP4 View? |
Daniele
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Caetano
The modification in note 351773 - Selection of production versions for planned order makes possible to select by order start date instead of finish date.
For my business logic explosion date in BOM explosion number should be used, so BAdI MD_MODIFY_PRODVERS seems to be the solution.
Thank you.