on 08-29-2014 10:42 AM
Hi
I have the requirement to change the score value on KPI level from the actual value to a fixed value:
Value Range in Score | Converted Score |
---|---|
<88 | 1|
>88<96 | 2|
>95<104 | 3 |
>103<111 | 4 |
>110 | 5 |
In the sample below I would like to replace the value 81.1 with the value 1 and the value 89 with 2
Any advice on how I can achieve this in SSM
Regards
Koos
the _TARDEV is a virtual variable with a formula for the score. You can replace the formula with a logic and put a case statement in there to calculate the values you require.