How works load distribution in tx. CM01

0 Kudos

Hi everyone,

I need to replicate the load distribution logic of CM01 in SAP BW, the customer need this information per day. The key is SAP060. But I don't understand how works the distribution.

I have an example: A operation starts the 02.10.2014 at 9:10:03 and finish the  03.10.2014 at 14:53:29, the time for this is 1,4+E01.  The operating type of this capacity is 8,5 hrs with 3 persons, an 100% of utilization, the total capacity is 25,5 H, the operating time starts at 08:00:00 and finish 17:06:00, the break is 00:36:00.

The transaction returns 7,56 for 02.10.2014 y 6,44 for 03.10.2014.

Can please somebody help me to understand what is the formula to get this result?.

Thanks for any help.  

Accepted Solutions (1)

Accepted Solutions (1)

marianoc
Active Contributor
0 Kudos

Hi Rosmar,

The distribution is done according to the available capacity (shifts and intervals) of your work center.

You can check the capacity in the work center (CR03), in the capacity view.

I had a similar requirement and we copied the standard CM01 program (and some of the includes) in order to get the exactly same result in an internal table. I recommend to do this. CM01 calls several functions, most of them not released, and its not so simple to replicate the logic.

Kind Regards,

Mariano

0 Kudos

Thanks for answer so quickly, I think that I'm going to do the same.

Have a good day Mariano.

Regards,

Rosmar