Hi,

SAP would initiate a purchase requisition  for a material item that had a MRP  type of “PD”.  This wouldhappen when the item was put on reserve against a work order by the maintenance or instrument/electrical folks.  The material type was ZMR0.

Is it possible in SAP? How? can some body give tips for this scenario?

With Regards,

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Jaheer

After a reservation from a PM order is created and there is not enough stock, a purchase requisition can be generated by MRP to cover the requirement.

You may manually run MRP for this material on transaction MD03 or schedule a background job to be executed and plan all the materials of a plant using transaction MDBT.

Just make sure that the value 1 is set for the parameter "create purchase requisition" of your job variant or in MD03.