on 09-12-2014 5:20 PM
I have a problem with periodic task "Revenue Recognition". When I launch the execution, for example, for the month of September, the system does not calculate the schare of accounting of revenue but it relize all amount of revenue. I want to understand why the system does not execute the right calculation.
Please can you explain me this situation?
Thanks
Hi Andrea,
I believe you are referring to accrual method "percentage of completion" calculation process
Lets take for instance Sales Order % POC calculation.
Calculated POC = ( Actual Cost / Estimated Cost ) * 100 %
For Item 123-10 , Calculated POC = ( 14277 / 8550 ) *
100 % = 166.98 %
For Item 123-20 , Calculated POC = ( 0 / 8550 ) * 100 % = 0 %
================
Also refer to
1.Revenue Recognition for Project Sales - help document
2.Revenue Recognition for Customer Contracts - help document this may help.
Thanks
Lokesh Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.