on 09-18-2014 7:53 PM
I am using dynamic safety stock with following config.
Period indicator W Week
Number of periods 13
Type of per.length 1 No. of Days per Period
Min. Tgt 30 Max. Number of Periods 4
Min. Tgt Max. Number of Periods
Min. Tgt Max.
I have material which has following requirement in MD04..Lead time is 130 days.I run the MRP and it calculated the dynamic stock. Please check the screen shot.
09/02/2014 IndReq VSF 100.00- 100.00-
10/01/2014 IndReq VSF 100.00- 200.00-
11/03/2014 IndReq VSF 100.00- 300.00-
12/01/2014 IndReq VSF 100.00- 400.00-
01/02/2015 IndReq VSF 100.00- 500.00-
02/02/2015 IndReq VSF 100.00- 600.00-
03/02/2015 IndReq VSF 100.00- 700.00-
04/01/2015 IndReq VSF 100.00- 800.00-
05/01/2015 IndReq VSF 100.00- 900.00-
For month of September it's running standard MRP which I understand but for October I can't understand how it's calculated 245.17.I have period 13 weeks that means 65 days. I am not sure how many days system is considering to calculate the daily requirement.
Can you please help me to understand ?
Hi MM KS,
The coverage only applies for October.
The system will not calculate any coverage for Novemeber, December, January, etc.. because in your coverage profile settings you said that you only want to consider the coverage for the following 4 periods (4 weeks).
So the MRP will generate a PurReq for 245.17 CS for Oct 1st. At the end of Oct you will have 145.17CS.
Because you don't want to have coverage for Nov, then you will see that the MRP is not creating any requisition for November (note that the PReq 0019945520 has an rescheduling message for 10.01.2014 and then following requisitions PReq 0019945521 has a scheduling message for 12.01.2014). So the system skip November.
At the end of Nov your projected stock would be 45.17 CS, so if you are going to have sales for 100CS, you have to buy 54.83 additional CS.
Hope this is clear for you.
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI MM KS,
No. The system is considering Total Demand = 300, this is divided by 62 days (13 weeks of your factory calendar). So the daily demand is: 4.8387 CS / day. This is multiplied by your target, that is 30 days. As a result, your safety stock is 30 x 4.8387 = 145.17 CS. Then the system buy 100 CS to cover the PIR + 145.17 CS to cover the safety stock, so the PurReq is 245.17CS.
Kind Regards,
Mariano
Mariano,
I was able to figure out the logic after your explanation .I still have 2 questions.
First thing which I couldn't not figure out is number of days... It's considering October 62 days,November 61 days and December 63.days and my 13 weeks goes till 19th December .I have 3 holidays in November.No holiday in October and December till week of 19th.
It's not a big deal but was just trying to understand the logic.
Second is we are using rounding value 48 days..it's creating a total requirement of 240 ...My guess it should create total requirements 288 as requirements are 145.16+100=245.16.I have the 2 screen shot one with rounding value and another one with out.Planned delivery time is 10 days.
Thank you again !
Hi MM KS,
I can not review how the system calculates your working days.. I would need to review your calendar, how many working days you have, the holidays and even to debug the system to see what is calculating in case I can not reproduce the number.. Now it seems to be a reasonable number what you have.
Regarding the second question, without the rounding value you had two requisitions on 10.07.2014, one for 100 CS and the other for 245.17 CS. now with the rounding the first requisition is increased to 144CS and the second one to 240 CS... This is correct. You don't buy 288 CS, because instead buying 100 CS you bought 144 CS in the previous order.
Let me know if this explain your doubts and please close the thread in case your main question was answered.
Kind Regards,
Mariano
Mariano ,
I know thread is closed ...but this number of days logic still not clear. With following parameter I am running the MRP.
Period indicator W Week
Number of periods 13
Type of per.length 1
Tgt 30 Number of Periods 26
Please see the result ...For February calculation is going out of the way Please check following
Hi MM KS,
Your logic is ok, but for the first period: October the system calculates 400 weeks as total demand.
This is because today is Sep 29th, and when calculating the daily requirements, the system considers the incoming 13weeks and also considers the PIR that you have in the current month. This is very weird, but you can read SAP help:
The system takes into account all requirements in the current period, even requirements that lie in the past but are still in the current period. For example, if the planning run is carried out in the middle of the month, then those requirements that were planned at the beginning of the month are also included in the calculation of the average daily requirements.
Calculating the Average Daily Requirements - Planning Process - SAP Library
So you should make again all your maths, but considering:
b. Forecast next 13 weeks 400 / 62 days = 6.4516 per
day *30 days = 193.55 safety stock +100 normal req =293.55 PR
Then you will be able to reproduce the calculation...
Kind Regards,
Mariano
Hi MM KS,
If you repeat your calculation, you will get this:
The system is considering 400 EA for February calculation, this is maybe because February has less days, and then 13 weeks cover still May 3rd...Look at the weeks:
W01 | 2-Feb | 8-Feb |
W02 | 9-Feb | 15-Feb |
W03 | 16-Feb | 22-Feb |
W04 | 23-Feb | 1-Mar |
W05 | 2-Mar | 8-Mar |
W06 | 9-Mar | 15-Mar |
W07 | 16-Mar | 22-Mar |
W08 | 23-Mar | 29-Mar |
W09 | 30-Mar | 5-Apr |
W10 | 6-Apr | 12-Apr |
W11 | 13-Apr | 19-Apr |
W12 | 20-Apr | 26-Apr |
W13 | 27-Apr | 3-May |
Note that you have forecast in Feb 2nd, Mar 2nd, Apr 1st and May 1st.
Kind Regards,
Mariano
Hi MM KS,
Thanks!
You can find everything thru google. I have lot of documentantion, but believe me, everything is already available in the web.
I would recommend to navigate the PP space in SCN. There are lot of very valuable documents and blogs loaded here by the different PP experts.
Here you will see different articles loaded by different SCN memebers...
If you know what you want, you can search in the SCN space or in google and you will get what you want.
Of course if there is something that you can't find after trying, you can open a thread.
Kind Regards,
Mariano
Hello Mariano,
hope you are doing good.We implemented dynamic safety stock.I have hard time to understand calculation of 1 material.
Following is the configuration we use for dynamic safety stock.
Period indicator W Week
Number of periods 13
Type of per.length 1 No. of Days per Period
Min. Tgt 30 Max. Number of Periods 26
If you see following example I can't understand how the requirement for 76 is coming.Material has rounding value 76 but still how the requirement is coming for 1 ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.