scheduling of preventive maintenance order

former_member223579
Participant
0 Kudos

Hi all,

I tied todo the IP10 transaction for scheduling the maintenance order.  assume that i enterd a requred datas. it is coming with 5 calls. but i tried this same data in a old system( pre upgradation), there it is showing only a 4 calls, which is a correct one.

my doubt is in what base the calls getting created. and the 1 extra call in new system comes beyond the date.

can anybody pls clarify my doubt.

( currently i am doing a upgradation testing ).

thank you ,

Siva-V


Accepted Solutions (0)

Answers (1)

Answers (1)

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Siva,

Can you please check what is the Scheduling Period that you specified in the Maintenance Plan data? Check the Scheduling Indicator and Factory Calendar too, if applicable. And, do the Plans start from the same date? Are the Task Lists valid for that date, or a later one?

Also, please can you post your Plans' scheduling parameters and schedule from IP10 if you want us to investigate further.