Dear Experts ,

                               As We know standard steps in PM-PP integration is ;

1. Putting PP work center in equipment master data

2. Assigning 'not in operation' in task list header

3. clicking " PM check box for reservation "

I want to know whether these steps are enough to control creation of PP work order when any maintenance is planned on that particular time or do we need to make use of any user exits to achieve the requirement.

Please help.

Regards

Keerthan Kumar

Accepted Solutions (1)

Accepted Solutions (1)

Private_Member_28603
Active Participant
0 Kudos

Hi Keerthan,

please take care, it's not enough to indicate in the task list system condition "0 - not in operation".

You have to specify the system condition separately in the maintenance item - click on the button "Task list detail" in maintenance item screen and then you have to maintain the system condition for the task list.

Now all orders created from this maintenance item will block capacity on the PP work center for the duration of the PM order.

Regards,

P

Answers (2)

Answers (2)

keerthan_1987
Active Participant
0 Kudos

Thank you , So it means we do not have to use any user exits ?


rakesh_mane
Active Contributor
0 Kudos

Hello

No user Exits required

Br

RAkesh

rakesh_mane
Active Contributor
0 Kudos

Hello

Might below document publish by K Kumar will help you.

http://scn.sap.com/docs/DOC-55261

Br