on 09-22-2014 7:20 AM
Hello Experts
Please explain the necessity to maintain inspection Point and QM control key in PM Task List.
Regards
Pravin Gautam
Hi,
If you want Inspection lot need to be created when we release maintenance order with inspection type 14. This will activate PM-QM Integration.
as given above - all links are helpful to you to use calibration management
Calibration of Measurement Instruments (PM/QM) - Quality Management (QM) - SAP Library
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Pravin Gautam
A combination of the Inspection Point (task list header) and Operation Control Key (inspection characteristic checkbox on task list operation) activate the PM/QM integration.
Useful info:
Calibration of Measurement Instruments (PM/QM) - Quality Management (QM) - SAP Library
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.