on 09-22-2014 11:44 AM
Dear All,
I want to know that there is any way to update the dates on work orders which is holding revision value.
our customer want to apply the changed values automatically or by mass.
please advise me and thanks for your help in advance.
Best Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi CHOI JIHOON,
As per suggested by Pete, for Single order you may process it going to iw32 --> Order --> Revision--> Refresh Dates.
If you want to do it in Mass you may:
1. go to IW38, give your selection (Revision in particular) for displaying the list of orders,
2. Select all the orders whose dates you wish to refresh,
3. Go to Order --> Revision --> Refresh Dates your order dates will be refreshed.
(For Mass you may use IW37N also as suggested by Pete but, that will give you list of Operations together with order).
Hope this helps.
Chin2.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.