Revision updation on work orders

choi_jihoon
Explorer
0 Kudos

Dear All,

I want to know that there is any way to update the dates on work orders which is holding revision value.

  1. user input a revision into work order
  2. user changes the dates on the revision.
  3. if user want to apply the changed date values, then user must change the work order by manual, need to input the same revision number once again.

our customer want to apply the changed values automatically or by mass.

please advise me and thanks for your help in advance.

Best Regards,

Accepted Solutions (1)

Accepted Solutions (1)

peter_atkin
Active Contributor
0 Kudos

Select the records in IW38 and use the following menu path:

Its the same in IW37N too..

PeteA

choi_jihoon
Explorer
0 Kudos

really working well, appropriate

Answers (1)

Answers (1)

former_member200331
Contributor
0 Kudos

Hi CHOI JIHOON,

As per suggested by Pete, for Single order you may process it going to iw32 --> Order --> Revision--> Refresh Dates.

If you want to do it in Mass you may:

1. go to IW38, give your selection (Revision in particular) for displaying the list of orders,

2. Select all the orders whose dates you wish to refresh,

3. Go to Order --> Revision --> Refresh Dates your order dates will be refreshed.

(For Mass you may use IW37N also as suggested by Pete but, that will give you list of Operations together with order).

Hope this helps.

Chin2.

choi_jihoon
Explorer
0 Kudos

Really thanks for your detailed procedure explanation!!