on 09-28-2014 4:45 PM
Dear PM Experts,
My client has centralized workcenter who can do maintenance tasks for more than one plant, and accordingly, I need to assign this work center to all the plants in the master data to be able to make the workcenter work in these specific plants. so it their is a way to assign one workcenter to more than one plant?
Thanks for your time, and cooperation.
All the best,
Mohammad Abdelrahman
+201221994984
Greetings Mohammed,
Are you using a centralised or de-centralised model for Maintenance Planning?
(i.e. Planning Plant to Maintenance Plant is 1:n or 1:1)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
To maintain one work center into more than one plant , create one work center separately in plant then copy from created work center to another work center which u want create for another plant from t code CR01. If ur client have no of work center & plant more then apply through LSMW.
lets do it & revert...
regards,
Amit Awasthi.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Mohammad,
Follow the following step
1) Create one centralized Planning Plant & assign to multiple Maintenance Plant as per you requirement.
SPRO- Enterprise Structure-Assignment-Plant Maintenance-Assign maintenance planning plant to maintenance plant
2) Create Work Center at Plant level
3) Create Task list at Planning Plant level.
4) Plan you maintenance activity at Maintenance Plant level by centralized Planning Plant.
Regards
Satish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Satish,
I've tried the process you described above before, but the point is the workcenter is assigned to the plant not the Planning plant, i.e: If you created plant 1000, it will be accordingly a maintenance plant 1000, then if you try to assign the work center to plant 1000, the system will accept, so it isn't assigned to planning plant but to maintenance plant or plant.
All the best,
Mohammad Abdelrahman
Dear Mohammad,
Please follow following steps :
1) Assign one planning plant to no- of maintenance plant.
2) Create Work center at Plant.
3) Create task list at Planning Plant
4) Create no-of equipment's at different Maintenance Plant.
5) Create maintenance work order for different equipment's with same work center.
Thanks
Satish
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.