Call Date manipulation based on frequency of each package in a plan

choi_jihoon
Explorer
0 Kudos

Dear All,

http://www.sapfans.com/forums/viewtopic.php?f=7&t=316460

my question is describes in above link, requirement is same with above link.

below is the copied contents from above link.


In the standard system, the call horizon % is based on the smallest package used in the maintenance plan..

We have a typical scenario where we want the call date to be 6 months earlier than the 3Y or 5Y inspection.

Has anyone managed to manipulate the call dates (not plan dates) in a maintenance plan via user-exit/BADI?

please help me is there any enhancement point?

Best Regards,

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member200331
Contributor
0 Kudos

CHOI JIHOON

Please check out the User Exits which might be of some help: EXIT_SAPLIWP3_004 and IPRM0002.

Hope this helps.

Chin2.

choi_jihoon
Explorer
0 Kudos

Dear Chin2,

thank you for your quick answer.

I think that I've tried with IPRM0002 and it didn't seem to work well.

I will try EXIT_SAPLIWP3_004, but my little concern is that "EXIT_SAPLIWP3_004" doesn't have changing parameter, it just have tables parameter only which may not relevant with "call date" field.

let me know your opinion.

thank you for your advice.