on 10-01-2014 2:22 PM
Hello,
I'm looking for a way to have budget cost in BW. The cube 0PM_C06 seems to be exactly what I need. I seen the solution MCB. I also found this document about Budget Planning and Maintenance Cost Reporting with SAP NetWeaver BW : http://help.sap.com/bp_utilities603/BBLibrary/Documentation/894_BB_ConfigGuide_EN_CN.doc .
In the document, they ask to activate and create object in the old version of BW. So, I want to know if there is a better way to have budget for PM. There is maybe a tool in a system other than BW.
Do you have a solution?
Regards,
Guirec.
Hi Guirec
You can maintain in table tpm_c05(SAP ECC) and use BW Data Source 0PM_PRM_PLCS_1 and do Budget Planning and Maintenance Cost.
We are currently doing the same in BI IP (Integrated Planning) and used 0PM_C05.
Rgds
Sri G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.