on 10-03-2014 6:11 AM
Hi,
I got this new requirement from one of the customer. Due to hardware unavailability client decided to Install BPC 10.1 on Virtual Landscape
and later on migrate it to HANA.
Installation of BPC 10.1 will be a straight forward approach. But, I am quite confused to figure out the Migration part.
In this scenario BPC version will be same, change will be at the Database and hardware level.
Initial plan is to follow below steps for this Migration activity.
Can you please let me know if I missed something or any other steps we have to cover for this activity.
Regrads
Basis
Hi,
Systematiclly speaking there is no issue in your thought process from Step-1 to 5.
Out of all the steps (5). I see the Step-3 (Restore/Import the BPC10.1NW) is a challenging step.
Cons
There is a change to fail due to the data base inconsisitencies. (RDBMS to IMDB)
Other wise there is no issue on your plan.
Hope this helps-Thank you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
3 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.