i want to know about checking horizon generally we mantained as 1 what does it mean .Is it related with requested delivery date little bit confuse
Example: I have product A whose sales order is created at 2nd october and requested date is 5th october which is proposed by system which is alrady defined I have block fom 8th october to 10 th october where orders sit in that block.
why system takes 10 th october .why not 8th october ?
.How it is calculation are done always it starts with end date of block . ?
In these scenerio where checking horizon plays role which is defined as one ?
3 different questions
Hi,
in APO end of checking horizon is determined in 2 steps.
First it is determined from checking horizon and from checking horizon calendar.
And then it is moved to the begining of the issue bucket (see oss note 952971 on that
topic).
Hope it helps to your questions.
Regards,
Tibor
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tibor,
What was the primary reason behind choosing Issue bucket instead of choosing reciept bucket ? If there are reciepts coming at a later point in time on the same day, then we dont consider those reciepts and we confirm the sales order at end of checking horizon right ? Does it make sense ?
Babu Kilari
User | Count |
---|---|
11 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.