on 10-21-2014 4:18 PM
Hello,
is it possible to convert planned orders to productions orders out of CM21, without to switch to MD04 or other screens?
Thanks,
Evgenij
Evgenij,
As far as I know you can not convert planned order to production order through CM21.
BR
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Evgenij
Maybe you should use the CO41, as Kiran told you, you cannot convert planed orders with CM21.
Best regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.