We're working with multi level BOM's in our prodcution process. So far we've setup several production orders to create the final good.

Is there a possiblity to include a multi level BOM in only production order?

Currently we're using the version 8.82. Are there further functionalities regarding the multi level BOM handling in any newer versions?

Many thanks for your answer!

Accepted Solutions (1)

Accepted Solutions (1)

kothandaraman_nagarajan
Active Contributor
0 Kudos

Hi,

It is not possible to create single production for multilevel BOM. Still you need each production order for each final item in multi level BOM.

Thanks & Regards,

Nagarajan

Answers (4)

Answers (4)

former_member188586
Active Contributor
0 Kudos

Hi

please check bellow  links  for phantom items..

Bills of Material

and check for Multiple BOM

Materials Requirements Planning

Thanks&Regards

Andakondaramudu

kothandaraman_nagarajan
Active Contributor
0 Kudos

Hi,

Please check this document:

http://wiki.scn.sap.com/wiki/pages/viewpage.action?pageId=21693348

Thanks & Regards,

Nagarajan

Former Member
0 Kudos

Hi,

Only if your multiple level BOM can be set as phantom items besides the top level, you can do it.

Thanks,

Gordon

Former Member
0 Kudos

Hi Gordon

Thanks for the answer. But what exactly do you mean with phantom items?

regards

Marcel

former_member205766
Active Contributor
0 Kudos

Hi

Not possible to create single production order for multi level BOM.

Definitely you need to create separate production order, Issue for Component and Report Completion for each BOM. 

One of my client using Addon WIP Addon for Creating Child level BOM so you can achieve this via SDK.

Thanks

With Regards

Balaji Sampath