Hello All,
We are trying to implement Availability control for cost centers, based on note 101030.
But it is not working, no error or warning messages are raised related to budget.
we are in ECC6, the note talk aboit R/3 but Isuppose it should apply as well on ECC6.
Did any one already get that issue or request ? any ideas ?
Hi,
Directly Cost Center Budget Availiability Control is not avaliable in SAP, suggested SAP Note delivers a work around:
A) Creating a Statistical Internal Order
B) Assigning Cost Center to the Statistical IO
C) Activate Avaliability Control for the Order
D) Budget Assignment to the IO
E) Book the expenses on IO
Refer SAP Note: 68366
Do revert in case any further details needed.
BR, Jaymin R. Bhatt
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you Jaymin
A) Has the Statistical Check box - Ticked in the Internal Order Master Data? --> Yes
B) Actual Posted CC - Has the Cost Center assigned in the IO Master? --> Yes in field CC requesting CC (and we added also to responsible CC)
C) Status of the Order--> "REL AVAC BUDG"
The cost can be booked if we put a cost center and the stat. IO, but can not be posted only with the stat IO. it give message requestng a real CO object KI248.
It can't be weird, the only thing would be that the Order Budget related configuration might have missing parameters.
Also check the Controlling Area Setting - OKKP, Order Management is Active.
A) Budget Profile - Check the Activation Type - Ideally "1"
B) Budget Profile - Check the Overall Value - if required
C) Assignment to Order Type -
E) Tolerance Limits - Check the Activity Group - Ideally "++"
F) Activation - "3" for Error message
G) Enter the Usage percentage - 90
BR, Jaymin R. Bhatt