Dear colleagues!

Currently I am looking if SAP in Product Costing, is capable of valuating, at batch level, the material produced based in the production notification event, with the specific real value of the raw material batches used, the specific real production costs, its scrap and its waste.

My question or doubt is if SAP in Product Costing is capable of valuating the batches produced in real costs, not only in Standard Cost, if so can you give some advice in getting this done in SAP.

Thanks for your comments.

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Victor,

     You can do product costing with actual cost other than standard cost. By using material ledger, you can full fill your requirement. While calculating it will plan cost only, after month end process, you will get actual cost. it will Revaluate all your material with actual cost.

Material ledger advantages are:

1) You can get actual cost of production at month end.

2) Multiple valuation and currency of your inventory.

Refer below notes for more understanding:

Actual Costing/Material Ledger - Actual Costing/Material Ledger (CO-PC-ACT) - SAP Library

Regards,

Kumar

former_member708103
Discoverer
0 Kudos

Many thanks for your reply...

All the best,

Victor Rincon