on 10-29-2014 9:33 AM
Hello,
we wanted to install SPS on ERP ECC 6 EHP 7 on HANA with SUM Version SUM10SP11_3.
In the Downtime the SUM stops with the error message:
>> Waiting for request handler...
>> Received 'next' action for unit 'EXECUTE'.
*** FATAL ERROR: Progress bar level 0 overflow 92 + 1 > 84
Execute Report RSUPGRES
Start a fresh SUM, but get this error message:
Component BP-ERP is in an undefined state, Upgrade wasn't completed - maybe upgrade was not reset ?
How can I fix the issue ? A restore is not possible because SAP Support take 2 months working on this ticket.
Thanks a lot
Start a fresh MOPZ and newest SUM. Clean table svers. Reset the upgrade via reports:
2053877 - Rücksetzen des Upgrades nach Notfällen
417670 - Ergänzungen zum Zurücksetzen des Upgrades ab Release 6.10
Now it works, but get another error
Thanks for your help !
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dieter,
Delete the entries from UVERS table.
But before this reset the previous upgrade and then delete the entries from UVERS table.
With Regards
Ashutosh Chaturvedi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.