Hi fellows
Actually I have the following setting dates
Then I put more resources to its "Engineering Documents" and got the following scenario
Now the activity "Document Engineering" ending 4/11/2014 and "Mobilizing Equipment" activity begins 14/11/2014, namely that there is a space of 10 days betwen this activities;
The WBS "Mov. / Const. PROVIC Facilities"It is not doing the reprogramming
How I can rescheduling the WBS and operations so bring dates back
Actually I have the following parameters: Bottom Up and programing ascendat
Please help me
Thanks in advance
I think, You have already raised same tread in the forum,
Kindly share the screenshot of Date tab of both the mobilization activities, You may have used Constraints to the activities as told by Maria resulting your path of activities got inflexible.
Thanks
Dnyanesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.