on 10-30-2014 4:56 AM
Hi Experts,
Need a suggestion urgently.
We have a work center , where we've mapped the start time and end time from 6:00 to 15:00 e.g. 9 Hrs
we have No of available capacities = 10
Hence total Available man-hours from 6 to 15 is = 9X10=90 Hrs
While i'm doing the capacity evaluation, system is distributing the required capacity Hrs in 9 and showing the requirement as 9 Hrs, 9 Hrs, 9 Hrs ....
Ideally it should first book the complete available capacity i.e.90 Hrs for a day..then should look for next day. But it's not happening in my case.
The formula I've used are as per the attachment .
Please help to find the reason...
Thanks
Hi Dennis,
Please check in CM03 and send us the screenshot
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
As per screen shot it is showing correct data e.g.for 08.12.2014 you have Total available Capacity is 90 hours for 10 numbers of Individuals.You required 9 hours for 08.12.2014 and remaining available Capacity is now 81 hours.System always doing calculation on the 24 hour basis which spread across on Day that is 08.12.2014. Which also follows the work Order Operation Earliest scheduled start Date and Earliest scheduled End Date with its time.for Next day that is 09.12.2014 if same work work order Earliest scheduled End Date falling then only that capacity hours get deducted from this report.
Br
Rakesh
My my issue is why system showing only 9 hrs as required capacity on a Single day, even though it's having ample of remaining capacity.
Ideally for a particular day , first it should book all the capacity required, then should move to another date. which is not happening here.
say Order#1, Operation #1 required capacity for a day = 45 Hrs
System is distributing it into 5 dates and booking capacity=9 hRS daily only.
Remaining 81 Hrs still remaining un-utilized ,even though available.
Please let me know ...if some setting need to be checked ..
Thanks
Hi Pete,
I've maintained the work center formula as depicted by you. Still the issue is same.
Also I've checked this in some other system as well still the issue reflecting same
Please check the operation time here. Although the available capacity on work center is 9hr X 5= 45 Man hours, still while scheduling the operation @ rate of 9 hrs/day (means it's not taking no. of capacities into account)
Can you please confirm this in your system ?
if this is correct, then where do the No.of capacity has an impact? how system will take it into account?
Seeking valuable suggestion from other experts also ...
Thanks
Hi Experts...
Please reply..
Please check ..in your system ..if it's behaving the same way for also, I'm getting e.g. in order operation , whether system still picking only 9 Hrs per day, irrespective of No. of capacity maintained.
If yes ..then what is the purpose of No. of capacity here..and how to map multiple Person as capacity at work order?
Regards
Hi Rakesh,
Looks this field is to relate with the HR
We do not use HR module. so unable to put any person no. here.
One question: Is there any way , we can schedule the early start date and time in operations , w.r.t.the "Duration" field.
Say work=50 hrs, No of capacity= 5, hence Duration=10 hRS
Can we do scheduling for early start and end date based on this"Duration"??
Thanks
Thanks all , for your prompt & detailed reply
In my case the work center formula was incorrect. I correct it ...got rectified now
Dennis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Please let me know which transaction you are using for Capacity Evaluation.
Br
Rakesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.