on 10-30-2014 6:30 AM
is it possible to change inspection lot plan after result recording made ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mishuang,
If you want to change results after UD, you can define the characteristic as a long-term char.
If it is a short-term char. you'll have to cancel UD by note 33924 and change results. Or you may consider cancel the inspection lot in t-code QA12, menu 'Usage decision' > 'Functions' > 'Cancel lot'. Then create a new one to record correct results.
Best regards,
Nancy
Hello Jayesh,
Its exactly Possible to change the Inspection Lot Plan after RR.
As:
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
GRN qty change is possible after taking UD reversal but still there is no option to change SPECIFICATIONS AND THERE RESULTS.
Bcoz when you process RR table entries updated and there is no way of change the lot results and specs.
there is only one way to cancel the lot and reassign the plan and regenerate the inspection lot after GRN.
Or other wise table level update in SAP which is not recommended.
Regards
Sorry ,I don't know your mean of inspection lot plan ?
After the RR before the UD you can change the RR.
BR
MZ
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jayesh, I didn't understand the term inspection lot plan!
Anand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.