on 10-31-2014 6:29 AM
Hello All,
When we do the technical completion of production order, system does not asks us the date, but the date on which it is done is recorded as the TECO date.
My requirement is that, I want to do the technical confirmation of production order in back date. Is this possible via any user exit / badi??? Please reply
Regards,
smart
Hello Smart
System does not ask for the completion date when setting the status TECO. This is the standard behavior and it cannot be changed on customizing or by any setting.
You may test BAdI WORKORDER_UPDATE to set a different value for this field (I have never tested myself and I don't know if it's possible).
BR
Caetano