Order teco date change

Former Member
0 Kudos

Hello All,

When we do the technical completion of production order, system does not asks us the date, but the date on which it is done is recorded as the TECO date.

My requirement is that, I want to do the technical confirmation of production order in back date. Is this possible via any user exit / badi??? Please reply

Regards,

smart

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Smart

System does not ask for the completion date when setting the status TECO. This is the standard behavior and it cannot be changed on customizing or by any setting.

You may test BAdI WORKORDER_UPDATE to set a different value for this field (I have never tested myself and I don't know if it's possible).

BR
Caetano

Former Member
0 Kudos

Hi All,

Any other response??

Regards,

Smart

Former Member
0 Kudos

Hi,

This is SAP standard you cannot give you're own date.

Try with exits PPCO0002, PPCO0007 I am not sure weather it will work are not.

Reards,

Ravi