on 10-31-2014 8:15 AM
Hi Experts,
Please confirm if it is possible to check the production (101 mvt) and its component consumption (261 -mvt) date-wise against a process order.
Regards,
Hi,
Follow this path.
COR3 -- Goto---List----Documented goods movement.
Regards,
Smart
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If I understood your requirement correctly, then go to COOISPI, select Documented goods movements in the List and enter Process Order number as input and execute... It is will show goods movements 101 and 261 for an order based on posting date...Correct me If I am wrong.
Regards
Rajasekar.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Experts,
Please note that we want to view the report in one screen.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.