ToC getting created in ChaRM Urgent Change Document

Former Member
0 Kudos

Hi Experts,

I am facing issue in urgent change document

Whenever we change the status from “In-Development” to “To Be Tested” of an urgent change document, a ToC is getting created in the background for the original TR. As far as i know This is not the standard behavior of the Urgent Change document.

Could you please help me in knowing what causing the issue.

i also tried using standard transaction type SMHF but the issue is same.

We are with Solution Manager 7.1 SP11

Thanks,

Veeresh K R

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello Veeresh,

It depends on what kind of maintenance cycle has been defined in the change management TAB of transaction SOLAR_PROJECT_ADMIN. Once you activate change management in this tab, it will setup certain activities based on the chosen maintenance cycle. Most likely the current phase of the maintenance cycle you have used does not directly allow changes to production and therefore uses ToC to apply the changes in your QAS system.