Forecast release to ECC multiplied by buckets in the DataView

Former Member
0 Kudos

Dear Gurus,

my DP PlanningArea is in months and I created a DataView and Time bucket of future 3 months. I check the quantities at the technical period level and they seem to be ok. However, when I release the forecast to ECC I see that the monthly quantities are multiplied by 3 which is my time bucket .

For Eg: In my Planning Book, Forecast figures per month is 15000 for 3 months and Time bucket is also future 3 months.But when forecast is released to ECC, it is showing as 45000 for all 3 months in MD61 in ECC demand Management.

Please help to resolve the issue.

Regards

Amit

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

there is an OSS note for this, I will look for it next time I check muy notes.

Regards,

J.

Former Member
0 Kudos

Hi Amit,

I never had this issue so I can give you just few ideas.

Delete forecast from APO and ECC. Then run consistency check for DP time series. Enter the forecast again in DP planning book. Try to use the t.code /SAPAPO/REL_TO_OLTP to release the forecast to ECC system. In the periodicity enter Monthly time bucket (very important). 

Thanks.