HI Experts ,

I have a requirement where we want to see in Mass BOM changes for Material.. I mean Last change date for materials in Bulk.

Is there any standard report?..I checked in CS80 there we should give the particular date.

Thanks,

Bhargavi

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

In CS80 it's not particular date, if you give 01.01.2010 from that date to till date system will show the changes.

Regards,

Ravi

former_member184737
Active Contributor
0 Kudos

Hello Nhargavi desai,

Please check with tcode CEWB. Select working area as 'SAP_BOM' for header details and 'SAP_ITEM' for component details.

Thanks