Hi ,
We are running a Program which runs at plant level( Ex: Plant X).
Material A is having Inactive PIRs as this is a LTP(Long Term Planning) and Simulated Planned Orders in this Plant X.
Can anyone suggest what is the procedure to delete or not to consider this Material A in the Program run at the Plant X level.
Please suggest.
Thanks.
Hello
You can define a material status on OMS4 with the setting LT planning message set to 'B - Error message'.
This status should be assigned to the material on tab MRP1 of the material master.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.