on 11-21-2014 6:39 AM
I have create a customer order which requires 1 KG of material on Nov.21, when I run MRP, plan order generated in Nov.28, I want to know how 11.28 is calculated, if I want to change to 11.22.2014, how to do?
Hello
I suppose that the planned order basic date was calculated in the past, therefore, MRP changes the start date for today and run forward scheduling.
One option to avoid this issue is to allow a planned order to start in the past on customizing (transaction OPPQ).
Another alternative is to reduce the in-house production time on the material master.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Siva,
Can you please check MRP 2 view of the Header Material if there is any In-house production maintained. Check if Scheduled margin key is maintained.
Also check in the components MRP 2 view if you have planned delivery time & GR processing time maintained.
Also check if the components stock is available on 21st November, or else it needs to be procured.
Regards
Pratik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.