Hi,
there are lots of standard report to check actual cost against wbs
CJI3 is one of best report for the same.
More S_ALR*
S_ALR_87009630 : plan actual comparison.
S_ALR_87010777
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Manish,
In addition to the RPSCO table which gives data at value category level - to get line item level cost, use tables COSS and COSP. Here again the value type should be 4 and 11 and the version as '0'.
hope this helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Manish,
You can use Table RPSCO and use value type as 4 for actual cost. if you want to check for the statitical cost as well take value type 11 as well..
you should pass the OBJNR for the WBS from PRPS table to fetch the details..
Hope it helps..
Regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.