Deallocated Planned Order retains Capacity Scheduled Status

Former Member
0 Kudos


When using CM40 to mass deallocate planned orders the checkbox for 'Capcity Scheduled' is still activated.

However when using CM25 to deallocate a single planned order the chechbox is deactivated.

Has anyone faced this scenario?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Anyone has any solution. As the planned order retains the double asterick, MRP won't affect these orders.

Regards,

Radhakrishnan

Former Member
0 Kudos

Hi,

Double asterick means capacity dispatched so after runing MRP it will not get change.MRP will not affect these orders.

If want to remove Firming the go to md15 and double click on planned order,there is a Firming Indicator check box remove tick mark and save.

Regards,

Ravi

Former Member
0 Kudos

Hi Ravi,

Thank you for your response.

On running CM40 to mass-deallocate planned orders, we want the indicator 'Capcity Scheduled' checkbox to be de-activated. This is happening in CM25 when deallocating single planned orders.

Any idea on this issue

Regards,

Radhakrishnan

kiran_kumar179
Active Contributor
0 Kudos

RK,

Ensure you are using same overall profile in both Online CM25 and Background CM40 transactions?

BR
KK

Former Member
0 Kudos

Hi KK,

Thank you for your response.

We are using the same overall profile

What other criteria should I be checking for this problem

Regards,

Radhakrishnan