Iam having four operation in routing  for a material

10-----In-house---------Material assigned to it

20----In-house--no material assigned to it

30-----PP02- sub contracted---- no material assigned to it

40----In-house---------no material assigned to it

is it possible to assign same raw material for  diiferent operation(30,40)

Accepted Solutions (1)

Accepted Solutions (1)

former_member184737
Active Contributor
0 Kudos

Hi Jayaganapathy,

      It's possible if you maintain the same material(raw material here) twice in your BOM with the required qty and assigned into different operation. Please check and revert back.

Thanks

Answers (1)

Answers (1)

dejoy
Active Contributor
0 Kudos

Hello,

You need to maintain component as many times as many operations you have.So that component will be available for each operation.