Hi,
Iam having four operation in routing for a material
10-----In-house---------Material assigned to it
20----In-house--no material assigned to it
30-----PP02- sub contracted---- no material assigned to it
40----In-house---------no material assigned to it
is it possible to assign same raw material for diiferent operation(30,40)
Hi Jayaganapathy,
It's possible if you maintain the same material(raw material here) twice in your BOM with the required qty and assigned into different operation. Please check and revert back.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
You need to maintain component as many times as many operations you have.So that component will be available for each operation.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.