We want to capture employee efforts (man-hours) against particular job/ activity. Since such particular job/ activity is not a part of any project, we think of creating a dummy project in SAP, link activities to that project and then ask employees to fill their time-sheets against that particular project/ activity.
Further to this, there will be no Customer for such project, no value, and no budgets. Purely speaking, it is only for the purpose of man-hour booking.
Please guide as whether this is feasible/ possible in SAP or not and if yes, then how to achieve this?
With regards,
Mukund Gandhi
Hi Mukund,
This is possible and completely standard. Just use a zero activity price in KP26, but maintain something else like Planned quantity or Capacity for the system to recognize the record.
BR
Paulo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mukund,
In standard SAP you can, talking about your system in particular I have no idea how heavily that is customized to accept only customer specific projects (maybe you have a mandatory customer field somewhere). In that case just create a dummy customer record if that is the case.
Paulo