on 11-21-2014 1:27 PM
Hi Everyone,
I have scheduled v3 job in job control. In jobcontrol it is showing as not maintained but it is running in sm37
I have deleted initialisation for my datasource.but the job is still running
Eg:i scheduled periodic job for 6 hours so my job should run for every 6hours but it is running 3 times for every 6 hours and after this job gets finished these jobs are in released state so how can i stop this periodic job
Thanks,
Kavya
Hi,
At SM37, you may find your job and keep it status as schedule.
take basis team help.
Even at LBWE, you can cancel you V3 job schedules or make it as red status there.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
if you received above message then V3 job was not active.
So you need to check which is job is scheduled ?
Other wise they may be used prorgam. so please check with your team.
please check prorgam name which start like RMBWV*XX.
last two digistes belongs your data source applciation number.
if your data source is 2LIS_11_HDT then XX = 11.
if program was scheduled then stop it.
At SM37 please find the job which specific to your data source.
later you can do cancel.
Take your team help.
Hi Kavya,
To remove the job from scheduling you need to go follow below steps:
1. Go to SM37
2. Select you job -> (top menu) Job -> Click on 'Released->Scheduled' or press 'Shift+F6'
then the job status will change from Released to Scheduled. The job will not run again until you schedule it back.
You need to do this for any job you want to stop.
Let me know if there are any questions.
Thanks
Amit
User | Count |
---|---|
84 | |
25 | |
12 | |
9 | |
6 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.