Dear SAP Guru,
I want to sale custom product which have no standard component. I mean customer order to build as his requirement and to make this I will provide some spares and labor. We have no PP and PM module. I do not want to create any Finished material because raw material component are not fixed. Or we can sale only service. What do I do for this process.
Best Regards,
Shoyeb
Hi,
The Best solution for your requirement is to use Service material (DIEN) with variant configuration.
In Variants, you can put the Characteristics as your components (services/questions/requirements). Use the selected values of different component for pricing.
While creating a sales order, your customer has to select the components i.e. dynamic using the Characteristics in the variant configuration, and based on those your pricing condition will trigger.
Try and revert
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Did you search for Standard MTO process ?
even in MTO you need to integrate PP, I dont think without PP you cannot use Material and labor cost to bill the customer on Actuals
Or we can sale only service. What do I do for this process.
If you want to sell only services, it should using service material using normal Sales order. But it will be limited to fixed cost only
please revert if you need any further help
thanks
santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
Do you want to show the sub-components to the customer or in Delivery ?
If so, you have to create a BOM material with all the possible combinations and while copying you can select or deselect the relevant material
And alternatively if you have PP integration, then while creating the production order you can manually enter the components which you want to use to make a final material
thanks
santosh
See that depend upon your business scenario, whether you want to show the subcomponent or not. I am saying take the service order process. Create sales order and then invoice
Material master also take as service material and if you want BOM explode in the sales order, then also you can create BOM ( for Sales and distribution ). Your wont required the PP for this