on 11-24-2014 3:49 PM
Hello,
I'm looking for a possibility to insert a characteristic in 1000 plans.
The new characteristic "B" is needed in every plan who has a characteric "A" yet. So it's no problem to find the relevant plans. But characteristic "A" is always in a different operation and has always a different Inspection plan characteristic number.
Whether the new characterist "B" is insert with Inspection plan characteristic number "777" that is free in any way or the more elegant solution would be that it gets the Inspection plan characteristic number directly after the characteristic "A".
Do you have an idea what could be a fast way to do this? It's not necessary that it works totaly automatic, but it shoul dnot take to much steps.
Thanks in advance.
Andrea
Hello Andrea,
Your all inspection plan which are having different specification values ?
If not then Its better to create new common inspection plan for all materials and that and do the material assignment to new inspection plan and mark deletion flag to old inspection plan.
You should take help from abaper for BDC of deletion of material asignment from old inspection plan through CWBQM.
Thanks,
Abhishek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Andrea,
Regards,
Natália
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You may want to refer this where I had gone with similar query last year. There is no standard way to assign a new MIC to multiple inspection plan at once (or atleast I haven't found it yet)
Yes correct, CWBQM can be used to for other purposes like replacing incomplete copy model MICs etc but not to assign a new MIC to carry out mass update.
Go for LSMW or BDC instead !
ntn
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.