Assign activity type to cost center

0 Kudos

Hello to All;

I have a new activity type and i need assign it to cost center. I would like know which transaction i can do It. I searched it on KL02 but i don't found where assign it.

Tks.

Accepted Solutions (1)

Accepted Solutions (1)

rajneesh_saxena
Active Contributor
0 Kudos

Hi

Use KP26/KP06 for the purpose.

I think at the time of PP settings you may be getting some message for this. If not, please give more description of error.

Regards

Rajneesh Saxena

Answers (2)

Answers (2)

0 Kudos

Tks to both. I did te test and a can see it.

Regards.

Former Member
0 Kudos

Hi Ricardo,

As Rajneesh has mentioned above, in KP26 you assign the activity type to the cost center and also do the price planning for that activity type/cost center combination.