on 11-26-2014 8:14 AM
Hi BPC Friends
I have created a new BPC Package in Development
Is possible to transport it or is better to create a new one in Quality and in Production?
How I can transport?
Thanks
Michele
You definitely can transport it.
RSA1 -> Transport Connection -> Object Types -> More Types -> Environment -> <<Select Your Environment and then select the object you need to transport.
Data Manager Packages selections is under the model
For more information:
http://scn.sap.com/blogs/ning/2013/03/27/sap-bpc-10-transport-guide
Cheers,
Lucas