on 11-27-2014 11:19 AM
Hi,
I am new to MSMP area.
I’d like to impose the ‘Risk approval workflow’ while Risks are being maintained. While trying to test the functionality , Risk approver didn’t get any email/notification. Appreciate your helpful comments /suggestion here.
I did the following things
Thanks,Krishna
I got it through -approvers are getting work items of risk changes !
It worked after I have removed 'LINE_ITEM_KEY' column in my BRF+ decision table for process id 'Access Risk approval WF'.
Thank you all who had given their suggestion on this!
Thanks,Krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thasks Madhu for your detailed response!
I understand now that all notifications configured in MSMP stages would require the above steps to trigger an email. In my system ,Email dispatcher has not been set up.
However without these steps , NWBC work item should be sent to risk owner which is not even happening in my case , not sure if i am missing any stpes?
As you told I cancelled all existing request of Risk approval WF type , and re-tried to submit the updated risk but ending with follwoing error.
Thanks,Krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Krishna,
Can you confirm if you have maintained the parameters 1101, 1102, 1103 with the risk approval request type ID? You can find this request type ID in SPRO under "User Provisioning" -> "Define Request Types".
If those are set fine, also check where your request is stuck at and let us know.
Thanks!
Sammukh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Krishna,
First please confirm if you have completed the below mentioned steps regarding mail notifications.
Please check all the below :
1. Did you complete post-installation step "Perform Automatic Workflow Customizing" via IMG.
2. Is the SAP Connect configured to send the emails?
SPRO--> GRC-->General Settings -->Workflow -->Workflow E-mail Notifications -->Set Up SAPconnect
Double click on SMTP and check the mail host and mail port is there or not.
3. Did you configured background job for Email dispatcher?
4. Does your system user WF-BATCH has proper Email ID maintained in SU01 in GRC system? Also please confirm if your system user WF-BATCH have proper authorizations.
5. Are you using standard notification settings at stage level or Did you customize the notifications? Are the "Notification Settings" in each stage with the events configured properly?
6. Check whether emails are getting triggered in SOST
7. Use Tcode SLG1 to see if any error is being triggered, also review workflows logs.
8. Go to MSMP instance monitor to see if any clue as to what has happened. Transaction is GRFNMW_DBGMONITOR_WD
Also if possible please post your stage notification settings screenshots to assist further.
You got error message when you tried to SUBMIT the Risk approval again because the earlier workflow created for the same risk ID is still open.
You can check from Search requests with MSMP Process ID as RISK APPROVAL wORKFLOW and close or cancel it and then can resubmit.